APPENDIX 2: SEWA INTERNATIONAL UK ONE YEAR PROGRESS REPORT (GUJARAT EARTHQUAKE)

Table 5: Sewa International UK’s report on progress in village reconstruction one year after the earthquake (ten villages)
ACTIVITY VILLAGE No houses Value Rupees Lakhs(i.e. 100,000) Value US$ Excavation PROGRESS OF HOUSES
RCC Footing Plinth Level Sill Level Lintel Level Slab Level Slab Casting
WORK STARTED MITHAPASVARIA 153 283.10 603,000 153 120 110 100 80 67 31
DEVGADH 211 361.45 770,000 162 143 115 88 58 53 32
MAYAPUR 81 237.50 505,000 77 63 53 48 39 33 16
JIVAPAR 208 372.10 790,000 173 170 155 108 77 61 61
HAMIRAMORA 23 36.60 78,000 23 23 20 18 15 12 4
JAKHOTRA 267 628.45 1,340,000 74 33 33 22 19 6 6
CHAPREDI 295 504.00 107,200 155 78 74 41 28
SURVEYING AND PLOTTING BEING DONE
SITE INAUGURATED VALLABHPUR 140 210.45 448.000 WORK IS NOT STARTED
VACHHARAJPUR 57 100.62 215,000
VISNAGAR 204 330.23 702,600 18
Source: Sewa International, Gujarat Earthquake – 26 January 2001 Anniversary Issue. One Year After, undated.

Table 6: Sewa International UK’s report on progress on the infrastructure facilities in village reconstruction one year later (ten villages)
DISTRICT GRAM MANDIR (VILLAGE HALL) PANCHAYAT GHAR (COMMUNITY CENTRE) HEALTH CENTRE SCHOOL
MITHAPASVARIA COMPLETED AT LINTEL LEVEL LINTEL COMPLETE
DEVGADH SLAB LEVEL SLAB LEVEL PLINTH COMPLETE
MAYAPUR PLINTH COMPLETE SLAB LEVEL
JIVAPAR   PLINTH COMPLETE SLAB LEVEL
HAMIRAMORA PLINTH LEVEL PLINTH LEVEL EXCAVATION IN PROGRESS
JAKHOTRA SLAB LEVEL SLAB LEVEL  
CHAPREDI        
VISNAGAR        
VACHHARAJPUR        
VALLABHPUR        
Source: Sewa International, Gujarat Earthquake – 26 January 2001 Anniversary Issue. One Year After, undated.

Table 7: Sewa International UK’s report on school building progress one year after the Gujarat earthquake
DISTRICT NO. SCHOOLS PROGRESS EXPECTED TO BE COMPLETED VALUE RUPEES (LAKHS) VALUE US$
WORK STARTED EXCAVATION PLINTH LEVEL LINTEL LEVEL SLAB LEVEL COMPLETED
BANASKANTHA 4 4 2 1 1 15th November 57.60 122,575
SURENDRANAGAR 9 9 2 2 2 3 15th November 82.60 166,196
JAMNAGAR 14 13 1 3 1 8 15th November 118.60 226,150
RAJKOT 4 4 1 1 2 15th November 80.40 171,085
KUTCH 21 21 2 5 1 11 2 15th November 248.50 514,285
PATAN 8 8 2 4 1 1 15th November 69.80 148,770
TOTAL 60 59 7 17 6 25 4 15th November 657.50 1,349,060
Source: Sewa International, Gujarat Earthquake – 26 January 2001 Anniversary Issue, One Year After, undated.